Schedulers

Definition

Every Workload has its own schedule. Those schedules can be activated, deactivated and modified.

A schedule is defined by:

  • Status (Enabled/Disabled)

  • Start Day/Time

  • End Day

  • Hrs between 2 snapshots

Disable a schedule

Using Horizon

To disable the scheduler of a single Workload in Horizon do the following steps:

  1. Login to the Horizon

  2. Navigate to Backups

  3. Navigate to Workloads

  4. Identify the workload to be modified

  5. Click the small arrow next to "Create Snapshot" to open the sub-menu

  6. Click "Edit Workload"

  7. Navigate to the tab "Schedule"

  8. Uncheck "Enabled"

  9. Click "Update"

Using CLI

workloadmgr disable-scheduler --workloadids <workloadid>

Enable a schedule

Using Horizon

To disable the scheduler of a single Workload in Horizon do the following steps:

  1. Login to the Horizon

  2. Navigate to Backups

  3. Navigate to Workloads

  4. Identify the workload to be modified

  5. Click the small arrow next to "Create Snapshot" to open the sub-menu

  6. Click "Edit Workload"

  7. Navigate to the tab "Schedule"

  8. check "Enabled"

  9. Click "Update"

Using CLI

workloadmgr enable-scheduler --workloadids <workloadid>

Modify a schedule

To modify a schedule the workload itself needs to be modified.

Please follow this procedure to modify the workload.